Analysis on Factors Causing Project Delays in Road and Highways Sector in India Using Relative Ranking Index Technique

Authors

  • Siddesh K. pai Email ORCID National Institute of Construction Management and Research (NICMAR), India
  • Neeraj Anand University of Petroleum and Energy Studies (UPES), India
  • Ankut Mittal University of Petroleum and Energy Studies (UPES), India

DOI:

https://doi.org/10.30564/jcr.v3i2.4157
Received: 29 November 2021 | Published Online: 17 December 2021

Abstract

On-time completion of road infrastructure projects is a critical goal. When
projects were not completed on schedule and real construction progress is
slower than expected, the inconvenience and disruption to business access
increases. On time completion is linked to economic and social welfare,
as well as safety. Construction delays continue to be a typical occurrence,
despite the need of prompt completion.
A literature study is conducted in this context in order to learn more about
the causes and factors that contribute to delays. Following a thorough
review of the literature, it was determined that a questionnaire survey is
the most effective and trustworthy way for gathering information about the
causes and quantifying delays caused by emergent factors. The Relative
Importance Index (RII) method was used to analyze the data, and the
reasons for the delay were prioritized according to their importance. This
study focuses on the emergent concerns/causes and reasons of concern
in road infrastructure projects, as well as how to priorities these issues
sequentially during the planning stage. This study survey can assist
construction companies doing business in India in understanding the
essential or sensitive issues that require special attention in order to conduct
their businesses smoothly in this country while employing appropriate
project management practices.

Keywords:

Relative importance index, Issues of concern, Delay factors, Road, Construction projects

References

[1] Aditi Dinakar, May 2014. Delay Analysis in Construction Project. Volume 4, Issue 5.

[2] Ashish D. Joshi1, Prof. Dr. S.D. Khandekar, June 2015. Project Management for Construction Projects: Improving Project Performance. Volume 02 Issue 03.

[3] Arditi R.D., Akan G.T., Gurdamar S., 1985. Reasons for Delays in Public Projects in Turkey. Construction Management and Economics. 3: 171-181.

[4] Assaf, S.A., Al-Khalil, M., A-Hazmi, M., 1995. Causes of Delay in Large Building Construction Projects. Journal of Management in Engineering. ASCE: 45-50.

[5] Eckert Scott Grant, Summer 2007. Inventory Management and Its Effects on Customer satisfaction. Journal of Business and Public Policy. Volume 1 Number 3, 1936-9794.

[6] Dennis Daina, R., Meredith Jack, R., 2000. An analysis of Process Industry Production and Inventory Management Systems. Journal of Operations Management. 18, 683-699.

[7] Desai Megha, Dr Bhatt Rajiv, March 2013. A Methodology for Ranking of Causes of Delay for Residential Construction Projects in Indian Context. Volume 3, Issue 3.

[8] Desai Megha, Rajiv Bhatt, 2013. Critical Causes of Delay in Residential Construction Projects: Case Study of Central Gujarat Region of India. Volume 4 Issue 4.

[9] Mahamid, I., Bruland, A., Dmaidi, N., 2011. Causes of delay in road construction projects Journal of Management in Engineering. 28(3) 300-10.

[10] Vasishta, N., Chandra, S., Asadi, S.S., 2018. Analysis of risk assessment in construction of highway projects using relative index method. 9(3) 1-6.

[11] Edison, J.C., Singla, H.K., 2020. Development of a scale for factors causing delays in infrastructure projects in India Construction Economics and Building. 20(1) 36-55.

Downloads

Issue

Article Type

Article