Development of a Fuzzy Fire Risk Evaluation Model for Building Construction Sites in Hong Kong

Authors

  • John F.Y. Yeung Email Division of Business, College of International Education, School of Continuing Education, Hong Kong Baptist University, Hong Kong, China
  • Daniel W.M. Chan Department of Building and Real Estate, The Hong Kong Polytechnic University, Hung Hom, Kowloon, Hong Kong, China

DOI:

https://doi.org/10.30564/jcr.v3i2.4106
Received: 17 November 2021 | Published Online: 17 December 2021

Abstract

Earlier research works on fire risk evaluation indicated that an objective,
reliable, comprehensive, and practical fire risk evaluation model is essential
for mitigating fire occurrence in building construction sites. Nevertheless,
real empirical studies in this research area are quite limited. This journal
paper gives an account of the second stage of a research study aiming at
developing a fuzzy fire risk evaluation model for building construction sites
in Hong Kong. The empirical research findings showed that the overall fire
risk level of building construction sites is 3.6427, which can be interpreted
as “moderate risk”. Also, the survey respondents perceived that “Restrictions
for On-Site Personnel” is the most vital fire risk factor; with “Storage of
Flammable Liquids or Dangerous Goods” being the second; and “Attitude
of Main Contractor” the third. The proposed fuzzy fire risk evaluation
model for building construction sites can be used to assess the overall fire
risk level for a building construction site, and to identify improvement
areas needed. Although the fuzzy fire risk evaluation model was developed
domestically in Hong Kong, the research could be reproduced in other
nations to develop similar models for international comparisons. Such
an extension would provide a deeper understanding of the fire risk
management on building construction sites.

Keywords:

Fire risk evaluation, Reliability interval method, Fuzzy set, Fuzzy synthetic evaluation, Building construction sites, Hong Kong

References

[1] Hong Kong Labour Department, 2008. Occupation￾al Safety and Health Statistics Bulletin Issue No. 7 2007. Hong Kong Special Administrative Region: Government Printer.

[2] Anonymous, Oct 26 2005. Fire in One Silver Sea, Ming Pao Daily News.

[3] Anonymous, Dec 2 2006. Fire in Mega Box, Sing Tao Daily News.

[4] Chan, A.P.C., Chan, D.W.M., Chiang, Y.H., Tang, B.S., Chan, E.H.W., Ho, K.S.K., 2004. Exploring critical success factors for partnering in construction projects, Journal of Construction Engineering and Management, ASCE. 130(2), 188-198.

[5] Yam, M.C.H., Yeung, J.F.Y., Chan, R.K.W., Wong, F.K.W., Chan, A.P.C., Chan, D.W.M., July 2009. Identification of fire risk criteria and attributes for building construction sites in Hong Kong. Proceed￾ings of the AUBEA Conference 2009 on “Managing Change: Challenges in Education and Construction for the 21st Century.” University of South Australia, Adelaide, Australia. 7-10.

[6] Yeung, J.F.Y., Chan, D.W.M., 2019. Developing a holistic fire risk assessment framework for building construction sites in Hong Kong, Journal of Construction Research. 1(1), 43-58.

[7] Lo, S.M., Lu, J.A., Hu, Y.Q., Fang, Z., 2001. Incorporating reliability and variance into weighting function of fire risk assessment for high-rise buildings, China Safety Science Journal. 11(5), 11-13. (in Chinese)

[8] Lo, S.M., Hu, B.Q., Liu, M., Yuen, K.K., 2005. On the use of reliability interval method and grey relational model for fire safety ranking of existing buildings, Fire Technology. 41(4), 255-270.

[9] Lo, S.M., 1999. A fire safety assessment system for existing buildings, Fire Technology. 35(2), 131-152.

[10] Saaty, T.L., 2008. Decision making with the analytic hierarchy process, International Journal of Services Sciences. 1(1), 83-98.

[11] Yiu, C.Y., Ho, H.K., Lo, S.M., Hu, B.Q., 2005. Performance evaluation for cost estimators by reliability interval method, Journal of Construction Engineering and Management, ASCE. 131(1), 108-116.

[12] Moore, R.E., 1979. Methods and applications of interval analysis. Philadelphia: SIAM.

[13] Xu, Y.L., Chan, A.P.C., Yeung, J.F.Y., 2010. Developing a fuzzy risk allocation model for PPP projects in China, Journal of Construction Engineering and Management, ASCE. 136(8), 894-903.

[14] Shen, L.Y., Wu, W.C., Ng, S.K., 2001. Risk assessment for construction joint ventures in China, Journal of Construction Engineering and Management, ASCE. 127(1), 76-81.

[15] El-Sayegh, S.M., 2008. Risk assessment and allocation in the UAE construction industry, International Journal of Project Management. 26(4), 431-438.

[16] Lu, R.S., Lo, S.L., Hu, J.Y., 1999. Analysis of reservoir water quality using fuzzy synthetic evaluation, Stochastic Environmental Research and Risk Assessment. 13(5), 327-336.

[17] Sadiq, R., Rodriguez, M.J., 2004. Fuzzy synthetic evaluation of disinfection by-products: A risk-based indexing system, Journal of Environmental Management. 73(1), 1-13.

[18] Hsu, T.H., Yang, T.S., 1997. The application of fuzzy synthetic decision to the human resource management, Fu Jen Management Review. 4(2), 85-100.

[19] Zhao, H.F., Qiu, W.H., Wang, X.Z., 1997. Fuzzy Integrative Evaluation Method of the Risk Factor, Systems Engineering - Theory & Practice. 7(1), 95-123.

[20] Yeung, J.F.Y., Chan, A.P.C., Chan, D.W.M., 2007. Development of a partnering performance index (PPI) for construction projects in Hong Kong: a Delphi study. 25(12), 1219-1237.

[21] Chow, L.K., 2005. Incorporating fuzzy membership functions and gap analysis concept into performance evaluation of engineering consultants – Hong Kong study, Unpublished PhD thesis,Department of Civil Engineering, The University of Hong Kong, HKSAR.

[22] Tah, J.H., Carr, V., 2000. A proposal for construction project risk assessment using fuzzy logic, Construction Management and Economics. 18(4), 491-500.

Downloads

Issue

Article Type

Article